“The charger turns on” is not a complete handover. Residents also need a safe parking and cable arrangement, working access, understandable support, and the records the building will need if equipment fails or the site changes.
Commissioning is the agreed demonstration and documentation that the installed system meets its project scope. It does not replace an electrical inspection, permit closeout, or code certificate. The qualified installer, inspector, utility, network provider, and building manager each have different responsibilities.
Confirm closeout by area
| Area | Ask the responsible person to confirm or provide | Resident or building-team check |
|---|---|---|
| Site and equipment | For each unit or port, record the installed market version, make, model, serial number, hardware or firmware, manual, bay, and approved configuration. | The assigned bays and signs match the resident information. Report physical damage, blocked access, exposed work, or a new trip or collision concern. |
| Electrical and authority sign-off | Record the project class and applicable code or standard edition, required review release, electrical testing, permits, inspection records, acceptance certificates, and utility notifications. A plan review is not the same as design approval, inspection, or permit closeout. | Keep copies in the building’s project records. Residents should not open equipment or perform electrical tests. |
| Function and controls | The installer demonstrates the project-defined charging, load-management, meter, and protective functions, including simultaneous use where the design supports it and the expected behavior when a limit is reached. Record the exact circuit, meter or sensor, and control boundary. | Walk through the resident journey from access to a completed session and confirm the demonstration matches the agreed service. Record limits and operating modes; do not change protective or current settings. |
| Access and payment | The operator confirms accounts, cards or other access methods, pricing or billing rules, help contacts, and treatment of failed sessions. | A nominated resident or manager confirms that authorized access works and instructions are usable. |
| Network and communications | The provider demonstrates the agreed online functions and records connection-loss and recovery behavior if the service depends on a network. | Record the escalation route and any limits on offline service; do not promise an offline feature that was not included or ask residents to simulate a fault. |
| Accessible use | The responsible designer or building representative reviews the route, parking, connector reach, controls, cable handling, signage, and instructions for the users the project serves. | Record unresolved access barriers and who will correct them. Apply the local accessibility requirements for the property. |
| Accounts and administrator access | Demonstrate activation and registration for every unit or port, intended-owner acceptance, administrator and resident workflows, recovery and billing contacts, and contractor access removal or transfer. Tesla’s product guidance calls for individual Wall Connector registration; Easee says transfer completes after the intended owner accepts. | Record authorized roles and the recovery process in the handover folder. Transfer credentials securely; never place passwords or access tokens in a shared project file. |
| Ownership and support | The building identifies who owns the equipment, pays recurring charges, books maintenance, handles faults, and approves later changes. | Give residents one current way to report an outage or safety concern. |
The exact acceptance checks depend on the equipment and contract. DOE’s commissioning framework for federal facilities offers a useful process shape—plan, investigate, implement, then hand off—but does not define an apartment EV charger test schedule. In Canada, NRCan’s multi-unit guide says the local inspection process and project conditions control. In Ontario, ask for the ESA Certificate of Acceptance when it applies to the work. In Great Britain, ask which distribution-network notification and building-control route the installer used and what documentation the project requires. Record any required pre-work plan review separately from the final electrical inspection or certificate; confirm the applicable code edition and project basis with the responsible professional.
Assemble a handover folder
Keep a current set of records in a place the manager and future maintenance provider can access:
- Approved drawings and the final route, including changes made during construction.
- Equipment make, model, serial number, warranty, and the parking spaces served.
- Electrical design assumptions and responsible professional, where supplied for the project.
- Permits, inspection results, electrical certificates, authority acceptance, and utility correspondence that apply.
- The commissioning demonstration, outstanding defects, corrective actions, responsible party, due date, and retest or closure evidence.
- Operating instructions, access and billing setup, network-provider details, support contacts, maintenance tasks, and emergency escalation.
- Future connection locations, metering or load-management information, and records of any grant or utility-program evidence.
Funding-program records are separate from universal handover requirements. For example, current OZEV guidance asks authorised installers to provide equipment and claim evidence under the particular grant process. Check the live program terms rather than assuming that a program’s photos, warranty, or model rules apply to every installation.
Check energy-billing measurement where it applies
For a Canadian building that uses measured kilowatt-hours to calculate a resident’s charge, ask the operator and billing provider to confirm the Measurement Canada requirements for the exact charger, transaction, and billing arrangement. The temporary dispensation may cover qualifying, already deployed equipment used exclusively by owners or renters living in multi-unit residential buildings, but device type, in-market date, and other program conditions apply. The EVSE owner must receive Measurement Canada’s written approval before relying on that route. It is not automatic approval for every unit or a replacement for electrical permits and inspection. If the owner relies on a dispensation, retain the approval letter and required device placard, assign responsibility for ongoing conditions, and record the approval’s expiry or next verification checkpoint. Confirm current eligibility with Measurement Canada before the service begins.
Close defects before opening service
Create a punch list for every incomplete item. Separate safety or approval issues from service improvements, name the party responsible, and agree how the correction will be verified. Do not open charging to residents while a required inspection, electrical certificate, safety correction, or permit closeout remains incomplete. A cosmetic or software issue may have a different response, but the building should disclose it and give a clear resolution date.
Once the responsible parties complete closeout, share an operating notice that explains which spaces are live, how residents gain access, how energy is measured or billed, where to get help, and what to do during an outage. The notice should match the service that was actually installed.
Use the installation sequence to plan the earlier handoffs and the garage route guide for physical safety and access questions.
Sources checked: 9 November 2026. Certificates, permit closeout, DNO notifications, inspection, and program evidence vary by jurisdiction and project.