BC Hydro’s multi-unit residential building (MURB) program has EV Ready planning and infrastructure routes, plus rebates for eligible Level 2 chargers. The current Participant Rebate Eligibility Requirements guide is dated July 15, 2026. Funding is first-come, first-served while funds last, so use the live program guide and obtain project-specific approval before committing money.

Choose the project route

The EV Ready route begins with a professional EV Ready plan (EVRP) that assesses shared electrical infrastructure and future charging demand. A complex can then seek infrastructure funding under that plan and apply for eligible chargers. An individual MURB resident may instead apply for a standalone charger rebate when the building meets the program rules; this still requires documented electrical planning.

Component Published standard maximum in the July 15, 2026 guide Main gate
EV Ready plan Up to 75% of eligible cost, to $3,000 Building representative; pre-approval is required
EV Ready infrastructure Up to 50%, to $600 per parking stall and $120,000 per complex Approved EVRP and project-specific pre-approval
EV Ready charger Up to 50%, to $1,400 per charger and $14,000 per building Qualifying EV Ready project and current approval terms
Standalone MURB charger Up to 50%, to $2,000 per charger and $14,000 per building Individual application requires consent, a qualifying plan/report, and pre-approval

Indigenous-owned MURBs have different published charger limits. The guide also limits strata corporations, co-ops, and rental-building owners to $14,000 in MURB charger rebates per fiscal year and an individual resident to one rebate over the life of the program. A maximum is not a promise of funding or a statement that funds remain.

Comparison of the B.C. EV Ready building-wide rebate path and the standalone resident charger path, showing consent, planning, pre-approval, work, and final documentation as distinct gates.

Prepare an individual standalone application

Since July 15, 2026, an individual applicant must obtain confirmation of pre-approval before any work starts. The applicant may be a unit owner or tenant with the property owner’s consent, but the building must meet the current criteria, including five or more units, shared electrical infrastructure, long-term residents, and dedicated off-street parking. Buildings constructed after August 31, 2022 are considered only under the guide’s stated case-by-case exceptions.

For an individual resident’s standalone application, provide a signed consent form with the applicable strata council, co-operative board, and/or landlord signature. A strata, co-op, or rental-building ownership organization may group resident charger installations in one application; the program guide recommends, but does not require, separate consent forms for that route.

The application must include one of the qualifying planning documents: an EV Ready plan, an electrical planning report (required for strata corporations with five or more units under provincial law), or an Opportunity Assessment from the CleanBC MURB Retrofit Program. If applying only for the standalone charger rebate, complete the work and file the required documents within six months after pre-approval. If applying for EV Ready infrastructure at the same time, the guide gives nine months. Submit any extension request before the applicable deadline.

B.C. rebate timing from route selection and pre-approval through the six-month standalone or nine-month EV Ready completion deadline, with separate consent and permit gates.

The former route to seek EV Ready plan reimbursement without pre-approval ended July 14, 2026. For current applications, start with the live guide and get written pre-approval before paying for eligible work.

B.C. rebate records showing who applies, which planning document qualifies, what pre-approval decides, and the separate installation and property approvals to keep.

Plan a building-wide EV Ready project

The EVRP rebate applicant must represent the strata council, co-operative board, or rental-building ownership company. The plan must be prepared by a qualified professional and should show an electrical solution that can meet the building’s daily Level 2 charging needs. Apply for pre-approval first. For an approved plan, the participant generally must submit the final application within nine months of the utility’s pre-approval confirmation; ask about an extension before that date if needed.

Use the program guide to confirm who may apply for infrastructure or charger components, whether the building meets the shared-infrastructure and construction-date criteria, what the plan must include, and which contractor, permit, invoice, and final-application records are required. If the design or scope changes, ask BC Hydro or FortisBC how the change affects eligibility before proceeding.

A rebate application is not strata or landlord permission, an electrical permit, or utility approval. Confirm the parking right and building approval first, then have a qualified electrician and local authority check capacity, design, permits, and inspection requirements. B.C. strata owners can use the separate strata request guide to understand the property process; the current BC Hydro guide controls funding steps and deadlines.