Geography: Toronto Hydro and Hydro One service territories in Ontario. Checked: October 12, 2026.
A utility’s capacity screen is not the same as an electrical assessment inside an apartment building. The utility reviews its service or distribution connection; a qualified electrical professional still needs to assess the building’s panels, loads, equipment, and wiring. First confirm which electricity distributor serves the property: Toronto Hydro and Hydro One processes do not apply across all Ontario service areas.
Toronto Hydro: optional screen, then a connection request
Toronto Hydro’s current EV charging page includes apartment and condominium stations owned or operated by a building owner or third-party provider. It offers an optional preliminary consultation for early project planning. The utility says its high-level report covers capacity at the connection point, possible upgrades, project complexity, and an estimated connection-cost range; the report is non-binding.
The page currently says Toronto Hydro will complete this feasibility assessment within 15 calendar days after receiving its Electric Vehicle Consultation Information Request. When the project is ready to proceed, the applicant chooses a service request for either an increase to an existing service’s peak load or a new EV-charging service. Toronto Hydro asks for a scaled site drawing showing proposed charger locations, site orientation and property lines, transformer or substation location, and the private-property duct path and its length.
The utility’s Load Capacity Map can help with preliminary area screening. Its FAQ says the map is a high-level, illustrative tool, updated approximately quarterly; it is not real-time, does not include connection-cost estimates, and does not replace a project assessment or utility approvals.
Follow the Toronto map to the right next step
| Stage | What it can provide | What remains open |
|---|---|---|
| Load Capacity Map | An area estimate based on annual feeder/substation peak load minus its planning limit; the map is updated about quarterly. It represents load connections such as EV chargers, not generation/export capacity. | It is illustrative, not real-time or specific to a building. A blank area or multiple/limited values should go to Toronto Hydro’s general capacity-assessment inquiry form. |
| Optional consultation | A high-level connection-point screen and non-binding planning report; Toronto Hydro says it responds within 15 calendar days of receiving its Electric Vehicle Consultation Information Request. | It is not the service application, internal building assessment, or approval. |
| Service connection request | A formal request for an existing-service peak-load increase or a new EV service, with a scaled site drawing and route information. Toronto Hydro recommends applying early, ideally before final civil plans, but no earlier than five years before energization. | The recommendation is Toronto Hydro’s timing guidance; it is not a deadline and does not apply to Hydro One. The utility must assess the specific request. |
| Utility offer and conditions | Utility-specific connection requirements, any expansion/offer sequence, and conditions for moving forward. | An offer does not assess downstream building panels and wiring or grant building permission. Hydro One’s sequence is described separately below. |
| Property-side design | A qualified electrical professional assesses the building system, loads, parking and proposed equipment. | The building design still needs to align with the serving utility’s connection point and applicable requirements. |
| Remaining approvals | Building decisions, permits, inspections, easements, and other authorities can be identified for the project. | Confirm the actual approvals and current timing before construction; a map or preliminary report does not authorize work. |
If the map shows no data, several values, or limited capacity, Toronto Hydro directs the applicant to request a capacity assessment through its online general inquiry form. A connection request is still required for detailed connection information, cost estimates, and approvals.
Hydro One: connection and expansion offers
Hydro One’s 2026 Appendix G covers non-residential Level 2 and Level 3 EV supply equipment requiring at least 240 volts, including multi-unit residential installations owned or operated by the building or a third-party provider. It describes an online connection or service-upgrade request.
If no expansion is required, the appendix says Hydro One will provide a firm, fixed-price offer within 60 days after receiving a complete application, subject to conditions such as permits, easements, and third-party approvals. If an expansion is required, the applicant first receives an estimated-cost offer. Proceeding may require staking or design costs; after design, Hydro One provides a firm fixed-price offer. The utility may also require a deposit or other service agreements.
What these utility steps do not establish
Neither a preliminary map nor a connection offer calculates how many chargers an apartment’s internal system can serve. The utility path also does not confirm building permission, equipment suitability, a final installation design, or inspection. Those questions depend on the property and the current requirements of the serving authorities.
Before submitting a request:
- Confirm the serving distributor and the project owner or applicant.
- Ask an electrical professional to assess the building and prepare the technical information.
- Gather the site drawing and charger-location details the distributor requests.
- Treat a map or preliminary consultation as an early screen, not an approval.
- Confirm current Conditions of Service, costs, permits, and timelines with the distributor before making a commitment.
Use the apartment building capacity assessment checklist for the property-side information and the installation process guide for later project steps.