The word “metering” can refer to several different things: the utility’s meter and account, a building’s internal meter, or data reported by a charging station. Those records may describe different parts of the electrical system. Knowing which one measures the EV chargers helps a building plan its next electrical and operating decisions.
What each arrangement records
| Arrangement | Supply path and utility account | Measurement boundary | Load-control boundary to confirm | Authority question |
|---|---|---|---|---|
| Resident’s utility meter | The resident’s service and utility account | Usually the whole account load; EV-only use needs a separate measurement point | Whether controls cover the charger, the unit service, or another defined group | Can the proposed route and account serve the stall, and who approves work through common areas? |
| Common-area utility meter | A building common service and account | Total energy behind that meter, including any other common loads on it | Whether management sees only the EV group or also the loads that constrain it | Who holds the account and can authorize data access or service changes? |
| Separate EV utility meter and account | A dedicated utility service/account for the EV supply, where offered | Total energy through that EV meter; not automatically energy by driver | Whether the proposed controls can monitor and act on the intended EV supply | Which utility options apply to this account, parking arrangement, and control design? |
| Submeter | Downstream of an existing utility meter; it does not create a utility account | Only the circuit, stall, or charger group where it is installed | Whether the control system uses the same equipment and loads as the submeter | Who may use the reading for cost allocation or billing under local rules? |
| Charger or network data | Data reported by charging equipment; it is not itself a utility supply path | Sessions or energy values from the reporting chargers and network | Which chargers, communications, and backend are inside the control group | Who can access, retain, export, or correct the data, and what meter validates it? |
A utility meter records energy for an account and electrical service. A submeter is downstream of that utility meter and measures only part of the system. Charger or network data may help an operator allocate use, but it is a separate data stream. Ask the electrical professional and utility to confirm which meter sees the proposed charging equipment.
In a UK Power Networks-served block, also identify who is responsible for the internal building network and who can make a distributor connection query. The UKPN flat-building guide explains that handoff; a BNO role does not by itself identify the electricity supplier, account holder, or billing arrangement.
Three B.C. utility examples
BC Hydro currently describes three options for multi-unit residential customers in its service area: using an existing common-use account, adding a separate account and meter for all EV charging, or, in some assigned-stall arrangements, installing a separate meter for an individual charger. Under the common-account and separate-EV-account options, a strata that recovers costs from drivers administers that process separately. Its guidance says individual meters require a layout review by an electrical contractor and are not compatible with the described load-management configurations.
These are BC Hydro arrangements, not a Canada-wide metering standard. The individual option may also depend on assigned parking and approval for electrical work. Check the current conditions for the building’s utility and account type.
There is an unresolved BC Hydro source conflict. The current public metering page says its three choices are mutually exclusive and says individual meters are not compatible with the described load-management configurations. BC Hydro’s April 2025 multiple-occupancy advisory, which remains listed on its distribution-standards page, describes some combinations as permitted. Those published sources do not establish whether the advisory was superseded or applies to a different configuration. Do not assume mixed options are available: ask BC Hydro to confirm the actual account, parking arrangement, supply path, and proposed controls before relying on one.
Questions to answer before choosing
- Which utility account and electrical service will supply the chargers?
- Does that meter also supply hallways, lifts, ventilation, or other common equipment?
- Will one shared meter cover all charging, or will there be measurement by charger, stall, or circuit?
- Who can access utility, submeter, or charger-session records, and how long will those records be kept?
- Can the proposed meter arrangement work with the load-management design?
- Which building, utility, accounting, privacy, or local rules govern cost recovery?
Metering is one input to an operating model. It does not by itself determine who may bill whom, what rate is fair, or whether a wiring arrangement has capacity. For those choices, continue to the guide on metering and billing for shared charging and include the system layout in the building capacity assessment.